Skip to main content
Home

STAY INFORMED

Sign up for updates and alerts from the Maryland Transportation Authority.

 

PROJECT SCHEDULE

What is the anticipated schedule for completion of the Nice Bridge Improvement Project?

Project planning studies for the Nice Bridge Improvement Project have been completed by the Maryland Transportation Authority (MDTA), which identified alternates, determined environmental and community impacts, and gathered public input on the project.

Key milestones in the Nice Bridge Improvement Project project planning studies schedule were:

2006

  • Summer - Initiated Project Planning Studies
  • Fall - Developed Purpose and Need and Preliminary Alternates

2007

  • Spring - Held Alternates Public Workshop(s)
  • Fall - Performed Detailed Analyses (environmental, noise, community, air, etc.)

2008

  • Spring/Summer - Continued to perform Detailed Analyses (environmental, noise, community, air, etc.)
  • Fall - Conducted engineering to incorporate bicycle options. Submitted Draft Environmental Document to FHWA.

2009

  • Spring/Fall - Circulated Draft Environmental Document for Public Review and Comment
  • Fall - Conducted Public Hearing(s)

2010

  • Spring - Identified MDTA Preferred Alternate
  • Summer - Prepared Preferred Alternate and Conceptual Mitigation Package
  • Fall - Assembled Draft Final Environmental Document

2010/2011

  • Winter 2010 - Fall 2011 - Circulated Final Environmental Document

2012

  • Fall - Obtained Approval of Final Environmental Document*
  • Fall - Completed Project Planning Studies

*This project is now a candidate for MDTA capital improvement project funds. Funding is not currently available for future phases, including final design and construction.


2013

  • Spring - Partial Preliminary Engineering phase began.
  • Summer - Preliminary Engineering and Right-of-Way underway.

Logo Footer

WAS THIS PAGE HELPFUL?

Public Calendar

Dec 04

Finance and Administration Committee Meeting - December 4, 2025

9 AM

Livestream

This public meeting is livestreamed and archived on the Finance and Administration Committee Meeting Homepage. The Finance and Administration Committee Meeting homepage also provides access to the virtual meeting, schedule, agenda, materials and minutes.

Dec 16

Key Bridge Rebuild Virtual Community Update

6 PM

Virtual Zoom Meeting

MDTA invites you to a Virtual Community Update on the Key Bridge Rebuild Project.

Join us to hear the latest information including pre-construction activities, factors influencing estimated cost range and schedule, design elements, upcoming construction activities, and commuter resources.

Dec 18

MDTA Board Meeting - December 18, 2025

9 AM

Livestream

This public meeting is livestreamed and archived on the MDTA Board Meeting Homepage. The MDTA Board Meeting homepage also provides access to the meeting schedule, materials, agenda and minutes.