Skip to main content
MDTA Home
Drive Sober or Get pulled over - MDTA Police are arresting Impaired Drivers - Follow link to learn more.
Phase 1 South Toll Rate Range Setting Process - Comments Accepted until August 12, 2021
Traveled a Maryland Toll Road Since July 2020?
Go Early and Stay Late 1-877-BAYSPAN - Cross the Bay Bridge early Morning or late night.
Shift into drive: what keeps Maryland moving? DriveEZMD.com
Drive Sober or Get Pulled Over - MDTA Police are arresting impaired drivers - Follow link to learn more
Traveled a Maryland Toll Road Since July 2020?
Go Early and Stay Late 1-877-BAYSPAN - Cross the Bay Bridge early Morning or late night.
Shift into drive: what keeps Maryland moving? DriveEZMD.com
Nice Bridge Attention Waterway Users

PROJECT SCHEDULE

What is the anticipated schedule for completion of the Nice Bridge Improvement Project?

Project planning studies for the Nice Bridge Improvement Project have been completed by the Maryland Transportation Authority (MDTA), which identified alternates, determined environmental and community impacts, and gathered public input on the project.

Key milestones in the Nice Bridge Improvement Project project planning studies schedule were:

2006

  • Summer - Initiated Project Planning Studies
  • Fall - Developed Purpose and Need and Preliminary Alternates

2007

  • Spring - Held Alternates Public Workshop(s)
  • Fall - Performed Detailed Analyses (environmental, noise, community, air, etc.)

2008

  • Spring/Summer - Continued to perform Detailed Analyses (environmental, noise, community, air, etc.)
  • Fall - Conducted engineering to incorporate bicycle options. Submitted Draft Environmental Document to FHWA.

2009

  • Spring/Fall - Circulated Draft Environmental Document for Public Review and Comment
  • Fall - Conducted Public Hearing(s)

2010

  • Spring - Identified MDTA Preferred Alternate
  • Summer - Prepared Preferred Alternate and Conceptual Mitigation Package
  • Fall - Assembled Draft Final Environmental Document

2010/2011

  • Winter 2010 - Fall 2011 - Circulated Final Environmental Document

2012

  • Fall - Obtained Approval of Final Environmental Document*
  • Fall - Completed Project Planning Studies

*This project is now a candidate for MDTA capital improvement project funds. Funding is not currently available for future phases, including final design and construction.


2013

  • Spring - Partial Preliminary Engineering phase began.
  • Summer - Preliminary Engineering and Right-of-Way underway.

Logo Footer

WAS THIS PAGE HELPFUL?