Stage One
April 2018
Construction on the I-895 Bridge Project began with lane widths reduced to 11 feet and work taking place on the shoulders and under the I-895 Bridge.
Stage Two
November 27, 2018
Northbound I-895 will close 24/7 and two-way traffic will operate on Southbound I-895. The Holabird Ave. exit ramp will close 24/7.
Spring 2019
Northbound I-895 tunnel bore will close 24/7 for 60 days. Two-way traffic will operate in the Southbound bore.
Stage Three
Spring 2020
Southbound I-895 will close 24/7 and two-way traffic will operate on Northbound I-895. The Holabird Ave. ramp will reopen.
Spring 2020
Southbound I-895 tunnel bore will close 24/7 for 60 days. Two-way traffic will operate in the Northbound bore.
Stage Four
Summer 2021
Work on shoulders and final paving. Both Northbound and Southbound I-895 will maintain two lanes in each direction. The project is scheduled for completion in 2021.