Skip to main content
MDTA Home
Tier 2 NEPA Study
Go early Stay Late
6 Knot Speed Limit in the area of the Nice Middleton Bridge Project
Civil Penalties Waver Period now in effect - Ending 11:59p.m. November 30, 2022
Bay Bridge Crossing Study Tier 1 NEEPA Study The FEIS / ROD is now available.
Bay Crossing Study Tier 2 NEPA
Go early stay late.  More beach less traffic. 1-877-BAYSPAN
Civil Penalty Waiver Grace Period
Bay Crossing Study Tier 1 NEPA - THE FEIS / ROD is now available.
Focus in work zones -Slow down and stay alert - Drive like you work here.

Stage One

April 2018

Construction on the I-895 Bridge Project began with lane widths reduced to 11 feet and work taking place on the shoulders and under the I-895 Bridge.

Stage Two

November 27, 2018

Northbound I-895 will close 24/7 and two-way traffic will operate on Southbound I-895. The Holabird Ave. exit ramp will close 24/7.

 

Spring 2019

Northbound I-895 tunnel bore will close 24/7 for 60 days. Two-way traffic will operate in the Southbound bore.

Stage Three

Spring 2020

Southbound I-895 will close 24/7 and two-way traffic will operate on Northbound I-895. The Holabird Ave. ramp will reopen.

 

Spring 2020

Southbound I-895 tunnel bore will close 24/7 for 60 days. Two-way traffic will operate in the Northbound bore.

Stage Four

Summer 2021

Work on shoulders and final paving. Both Northbound and Southbound I-895 will maintain two lanes in each direction. The project is scheduled for completion in 2021.