Skip to main content
MDTA Home
Key Bridge News

Fort McHenry Tunnel

I-95 Carroll Camden Access Study

EXECUTIVE SUMMARY

The Maryland Transportation Authority (MDTA) initiated the current I-95/Carroll Camden Access Study to help determine whether or not to conduct a project planning study under the National Environmental Policy Act (NEPA). The current study, which is anticipated to be completed in late 2012, was launched as a follow-up study to the 2004 I-95/Carroll Camden Access Feasibility Study. The purpose of this new study is to:

  • Investigate current operations and safety along I-95 between Caton Avenue and Hanover Street
  • Further develop and evaluate alternatives that provide new or modified access to I-95 from the Carroll Camden development area while protecting the integrity of the Interstate System
  • Determine if Draft Preliminary Interstate Access Point Approval (IAPA) is feasible for any of the alternatives developed.

The study area is located in the southwestern portion of the City of Baltimore, and is bounded by I-95 to the south, Martin Luther King Jr. Boulevard to the north, Hanover Street to the east and Caton Avenue to the west. The study area includes the I-95 interchanges with I-395, MD 295/Russell Street, Washington Boulevard, and Caton Avenue, as well as major surface streets within these boundaries.

A crash history analysis and a capacity analysis were performed for the freeways and interchanges in the study area under Existing conditions. Capacity analyses were also performed using CLA for surface street intersections and HCS+ for freeways and interchanges for Existing and 2035 No-Build and Build conditions. VISSIM, a state-of-the-art traffic simulation software package, was used to perform a simulation of No-Build and Build conditions during both the AM
and the PM peak hours.

The study team used the recommendations from the 2004 Feasibility Study as a starting point for the development of new concepts that could better meet the project goals. The team examined each of the access points along I-95 within the study area, and noted the places where there were "missing movements," or places where drivers were restricted from traveling in a particular direction due to roadway geometrics, ramp configurations, etc. Using the results of the traffic analysis, the team then considered ways to provide new access to Carroll Camden by adding these "missing movements," and, through a series of meetings and discussions, created 12 new preliminary concepts.

Based on the suggestions and feedback from at the study team, which was made up of representatives from MDTA, Federal Highway Administration (FHWA), Baltimore City Department of Transportation (BCDOT) and the Baltimore Development Corporation (BDC), elements of the 12 preliminary concepts were combined to create four possible improvements to be forwarded for more detailed study. These are identified as Concepts A, B, C and D. These
combined concepts represent low, medium, and high levels of cost, with Concept C representing the lower level of cost, Concept B the medium level, and Concepts A and D the higher level cost options.

 

Concept A consists of the construction of a new collector-distributor (C-D) road along southbound I-95 between MD 295/Russell Street and Caton Avenue, and an extension of the existing C-D road along northbound I-95 from Washington Boulevard to east of MD 295/Russell Street. The neat construction cost, which includes highway design, bridge design, traffic engineering and utility costs but excludes right-of-way, is estimated at $365 million in 2009 dollars.

Concept B consists of the construction of a new flyover ramp connecting the southbound I-95 to southbound MD 295/Russell Street off-ramp to westbound Monroe Street, and a new ramp connection from the intersection of Monroe Street and Annapolis Road to northbound I-95. The neat construction cost (excluding right-of-way) is estimated at $72 million in 2009 dollars.

Concept C consists of constructing ramps to provide all missing movements at the interchange of I-95 and Washington Boulevard, closing access to the existing northbound I-95 C-D road north of Caton Avenue, and re-constructing the on-ramp connection from Caton Avenue to northbound I-95. It also involves closing the existing ramp from southbound MD 295/Russell Street to southbound I-95 to prevent the introduction of a weaving section due to the new Washington Boulevard off-ramp. The neat construction cost (excluding right-of-way) is estimated at $17 million in 2009 dollars.

Concept D consists of removing all existing ramps at the I-95/MD 295/Russell Street interchange and replacing them with a series of ramp connections from southbound I-95 to MD 295/Russell Street and from MD 295/Russell Street to southbound I-95, from MD 295/Russell Street to westbound Monroe Street, from northbound I-95 to MD 295/Russell Street and from MD 295/Russell Street to northbound I-95. The neat construction cost (excluding right-of-way) is estimated at $272 million in 2009 dollars.

These concepts are shown in detail in this report. The microsimulation analysis of northbound I-95 shows that Concept A works better during the AM peak hour than any of the other improvement concepts, due to the elimination of the weaving area between the Caton Avenue on-ramp and the MD 295/Russell Street off-ramp. During the PM peak hour, Concept A works better than the others, but offers no real improvement over the existing I-95 network. The analysis of southbound I-95 shows that Concept A works slightly better than any other concept, but the differences are minimal.

While the preliminary engineering shows that improvements to access between I-95 and the Carroll Camden area are geometrically feasible, they would be complex and costly. Preliminary analyses revealed that Concept D would likely be impractical to build because of its high cost and the fact that there does not appear to be a practical means of maintaining traffic on the existing directional ramps during construction. Under the current guidelines, IAPA requirements must be met any time existing interstate ramps are modified or relocated. In cases where the FHWA-required one mile spacing between ramps is not met, a design exception may be necessary. As all four of the proposed improvement concepts involve adding or modifying access to I-95, any improvement concept retained for more detailed design would have to meet the criteria necessary for IAPA. Members of the study team met with representatives from FHWA to review the improvement concepts and solicit their feedback. FHWA's review of the preliminary improvement concepts determined that none of them were likely to meet IAPA requirements because the proposed changes would not meet the one mile spacing requirement between interchanges. The required close spacing of ramps would lead to unacceptable merge and diverge distances and create additional operational issues on I-95.

 

ADDITIONAL INFORMATION:

For a copy of the complete study, please contact the MDTA's Division of Capital Planning at 410-537-5670.

WAS THIS PAGE HELPFUL?

Public Calendar

Apr 04

Capital Committee Meeting - April 4, 2024

9 AM

Livestream

This public meeting is livestreamed and archived on the Capital Committee Meeting Homepage. The Capital Committee Meeting homepage also provides access to the virtual meeting, schedule, agenda, materials and minutes.

Apr 11

Finance Committee Meeting - April 11, 2024

9 AM

Livestream

This public meeting is livestreamed and archived on the Finance Committee Meeting Homepage. The Finance Committee Meeting homepage also provides access to the virtual meeting, schedule, agenda, materials and minutes.

Apr 25

MDTA Board Meeting - April 25, 2024

8 AM

Livestream Event

This public meeting is livestreamed and archived on the MDTA Board Meeting Homepage. The MDTA Board Meeting homepage also provides access to the meeting schedule, materials, agenda and minutes.