Stage One

April 2018

Construction on the I-895 Bridge Project began with lane widths reduced to 11 feet and work taking place on the shoulders and under the I-895 Bridge.

Stage Two

November 27, 2018

Northbound I-895 will close 24/7 and two-way traffic will operate on Southbound I-895. The Holabird Ave. exit ramp will close 24/7.

 

Spring 2019

Northbound I-895 tunnel bore will close 24/7 for 60 days. Two-way traffic will operate in the Southbound bore.

Stage Three

Spring 2020

Southbound I-895 will close 24/7 and two-way traffic will operate on Northbound I-895. The Holabird Ave. ramp will reopen.

 

Spring 2020

Southbound I-895 tunnel bore will close 24/7 for 60 days. Two-way traffic will operate in the Northbound bore.

Stage Four

Summer 2021

Work on shoulders and final paving. Both Northbound and Southbound I-895 will maintain two lanes in each direction. The project is scheduled for completion in 2021.

WAS THIS PAGE HELPFUL?

Public Calendar

Oct 03

Capital Committee Meeting - October 3, 2024

9 AM

Livestream

This public meeting is livestreamed and archived on the Capital Committee Meeting Homepage. The Capital Committee Meeting homepage also provides access to the virtual meeting, schedule, agenda, materials and minutes.

Oct 10

Finance and Administration Committee Meeting - October 10, 2024

9 AM

Livestream

This public meeting is livestreamed and archived on the Finance and Administration Committee Meeting Homepage. The Finance and Administration Committee Meeting homepage also provides access to the virtual meeting, schedule, agenda, materials and minutes.

Oct 16

MDOT Engineering Positions Career Event at MDOT SHA

10 AM

Baltimore City HQ building
707 N. Calvert Street

We're hiring!

The SHA is hosting a career event for engineering positions throughout MDOT, including the MDTA, on October 16th from 10am to 3pm at its Baltimore City HQ building (707 N. Calvert Street).

Follow link to the Event Flyer in order to preregister.