Skip to main content
MDTA Home
Tier 2 NEPA Study
Go early Stay Late
6 Knot Speed Limit in the area of the Nice Middleton Bridge Project
Civil Penalties Waver Period now in effect - Ending 11:59p.m. November 30, 2022
Bay Bridge Crossing Study Tier 1 NEEPA Study The FEIS / ROD is now available.
Bay Crossing Study Tier 2 NEPA
Go early stay late.  More beach less traffic. 1-877-BAYSPAN
Civil Penalty Waiver Grace Period
Bay Crossing Study Tier 1 NEPA - THE FEIS / ROD is now available.
Focus in work zones -Slow down and stay alert - Drive like you work here.

banner

I-95 Ramp Rehab Banner

I-95 Ramp Rehab Construction Schedule

Summer 2021: Work begins on Northbound MD 295 on-ramp to Northbound I-95. Expect multiple weekday and weekend ramp closures.

Summer 2021: Work begins on E. McComas St. on-ramp to Southbound I-95. Expect multiple weekday and weekend ramp closures.

Fall 2021: Work begins on Southbound I-95 off-ramp to Southbound MD 295 (Exit 52). Expect multiple weekday and weekend ramp closures. When this ramp is closed, an additional closure will be needed on the S. Hanover St. on-ramp to Southbound I-95.

Fall 2021: Stage 1 of work begins on Southbound I-395 leaving the city onto Southbound I-95. All work will take place behind a concrete barrier wall while maintaining two travel lanes for public use. Temporary closures may be necessary to transport materials.

Spring 2022: Stage 2 of work begins on Southbound I-395 leaving the city onto Southbound I-95. Expect two separate weekend ramp closures.

Spring 2022: Stage 3 of work begins on Southbound I-395 leaving the city onto Southbound I-95. All work will take place behind a concrete barrier wall while maintaining two travel lanes for public use. Temporary closures may be necessary to transport materials.

Winter 2022: Final inspection and project completion.