Anticipated Construction Schedule:

2019 - 2020

  • Bradshaw Road Overpass Reconstruction
  • Old Joppa Road Overpass Reconstruction
  • Northbound and Southbound Section 100 Noise Walls
  • Auxiliary Lane from MD 152 to MD 24 and MD 24/MD 924 Ramp Modifications

2020 - 2021

  • MD 24/924 Park and Ride Lot Construction
  • MD 152 Park and Ride Lot Construction
  • Off-Site Environmental Mitigation

2020 - 2023

  • I-95 ETL Northbound Extension from MD 43 to MD 152, Raphel Road Overpass Reconstruction, and Northbound Section 200 Noise Wall
  • MD 152 Interchange Reconstruction, I-95 ETL Northbound within the Interchange Area, and Northbound Section 200 Noise Wall
  • Clayton Road Overpass Reconstruction
  • Abingdon Road Overpass Reconstruction
  • Northbound and Southbound Section 200 Noise Walls
  • I-95 ETL Northbound Extension from North of MD 24 to Bynum Run
  • New Intelligent Transportation Systems
  • Off-Site Environmental Mitigation

2023 - 2026

  • MD 24 Interchange Reconstruction and I-95 ETL Northbound within the Interchange Area
  • Off-Site Environmental Mitigation

 